Archive for November 11th, 2009

Raised Floor Starts Going in

Wednesday, November 11th, 2009

The raised floor has started being installed at the Bournemouth collocation facility. This enables cold air to travel under the floor to the designated cold aisles as well as providing an area for cabling to be run in.

SL370914

The team hard at work installing the first section of the raised floor at the Bournemouth Colocation Facility.

SL370931

The raised floor at Bournemouth Colocation facility after one day of work.