Electrical Work Continues On Bournemouth Data Centre Facility

Tuesday, November 10th, 2009

The main electrical mains panels continue to be populated.

These components are vital the successful running of the facility and will allow us to deliver high capacity resilient power to customers.

SL370920

The automatic changeover switch installed at the Bournemouth collocation facility used by the generator system in the event of a power failure.

Extractor Fan Installed At Bournemouth Data Centre Facility

Tuesday, November 10th, 2009

An extractor fan has been installed at the Bournemouth Data centre which will vent the FM200 gas from the fire suppression system should it ever be needed.

This will allow the room to be made safe. Whilst FM200 gas is not extremely harmful to humans it’s not advisable to breathe it in so systems such as this should always be installed.

SL370915

The extractor fan, which will vent FM200 gas at the Bournemouth Colocation facility.